APPLICATION & MODIFICATION/TARIFF PETITION FEE

Upto 31st May, 2017
     
  Period CPI Rate Ratio
  April, 2017 216.30 1.8771
  September, 2008                                                                 (Base Rate) 115.23
     
Application & Modification Generation License Fee Rs. Rs.
    Actual Fee Fee with CPI
  upto to 1 MW                    40,000                  75,084
  More than 1 MW upto 10 MW                    80,000                150,168
  More than 10 MW upto 20 MW                  120,000                225,252
  More than 20 MW upto 50 MW                  160,000                300,336
  More than 50 MW upto 100 MW                  200,000                375,420
  Above 100 MW                  400,000                750,840
  MW Capacity in case of Generation facility shall mean the ISO Gross Capacity as mentioned in the application.  
Application & Modification Transmission License Fee    
  National Grid Co.                  200,000                375,420
  Special Purpose                  120,000                225,252
       
*  Application & Modification Distribution License Fee    
  upto to 1 MW                    40,000                  75,084
  More than 1 MW upto 2 MW                    60,000                112,626
  More than 2 MW upto 5 MW                  160,000                300,336
  More than 5 MW upto 10 MW                  240,000                450,504
  More than 10 MW upto 20 MW                  480,000                901,008
  More than 20 MW upto 50 MW                  800,000             1,501,680
  Above 50 MW               1,000,000             1,877,100
  *  MW Capacity in case of Distribution facility shall mean either (a). 85% of the accumulated installed or expected to be installed Transformation Capacity as mentioned in the application ort (b). 0.019% of the annual expected sales in MWh as mentioned in the application.
Fees Pertaining to Tariff Standards and Procedures Regulations 2002  
     
(i) (a)    Generation Licensees  Rs. Rs.
    Actual Fee Fee with CPI
  upto to 1 MW                    60,000                112,626
  More than 1 MW upto 10 MW                  160,000                300,336
  More than 10 MW upto 20 MW                  240,000                450,504
  More than 20 MW upto 50 MW                  320,000                600,672
  More than 51 MW upto 100 MW                  480,000                901,008
  Above 100 MW                  800,000             1,501,680
     
    (b)    Transmission Licensees    
  National Grid Co.                  800,000             1,501,680
  Special Purpose                  320,000                600,672
     
    (c)    Distribution Licensees    
  upto to 1 MW                    40,000                  75,084
  More than 1 MW upto 2 MW                    60,000                112,626
  More than 2 MW upto 5 MW                  100,000                187,710
  More than 5 MW upto 15 MW                  160,000                300,336
  More than 15 MW upto 25 MW                  240,000                450,504
  More than 25 MW upto 50 MW                  320,000                600,672
  Above 50 MW                  480,000                901,008
     
    (d)    Consumers    
(i) Industrial, Commercial and Bulk Consumers                    40,000                  75,084
(ii) Industry and Trade Association or other representative bodies                  160,000                300,336
(iii) Residential Consumers                      8,000                  15,017
(iv) Agricultural Consumers                      8,000                  15,017
     
(ii) Intervention Request                         160                       300
(iii) (a) Copies of transcription of record, decisions and order of the Authority (per page)                             2                           4
      (b) Audio Recording (per cassette)                           60                       113
      (c) Video Recording (per cassette)                         160                       300
     
Application for the Approval of Competitive Bidding    
  Upto 100 MW                  100,000                187,710
  101 to 500 MW                  200,000                375,420
  Above 500 MW                  300,000                563,130
     
NEPRA Upfront Tariff     
  Upto 01 MW                    20,000                  20,000
  Upto 10 MW                    50,000                  50,000
  11 to 100 MW                  100,000                100,000
  Above 100 MW                  200,000                200,000

 

Home | Site map | Contact us | Careers

Copyright 2010-11 National Electric Power Regulatory Authority. All Rights Reserved.