Authority Decisions - Consumer Affairs

ARCHIVE

 
Islamabad Electric Supply Company (IESCO)

09-06-2016

Decision of the Authority Regarding Motion for Leave for Review filed by Shifa International Hospitals Limited against the Decision of NEPRA dated July 03, 2015 in the matter of Writ Petition No. 2204/2008: Titled " Shifa International Hospital Vs IESCO"

View

06-07-2015

Decision in pursuance to the order of Honorable Islamabad High Court dated march 25, 2015 in writ

Petition No. 2204/2008 in the matter of M/s Shifa International Hospital, Ltd vs IESCO, etc

Complaint # IESCO-63/2015

View

16-04-2015

Decision in the Matter of Complaint Filed By Ms. Saddiqa Bibi D/O Zulfiqar Ali under Section 39 of Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against IESCO Regarding Correction of Bill and Replacement of Meter (Ac#03 14123 0383700)

 Complaint # IESCO-143/2014

View

23-12-2014

Appeal filed by IESCO against the decision of NEPRA Tribumal in the matter of Al-Qaim Textile Mills Limited regarding Revovery of Energy Units lost in respect of 11 KV Independent Feeder w.e.f. April 2011 to May 2013 Complaint # IESCO-42-2014 View

12-09-2014

Decision in the Matter of Complaint Filed By Mr. Iftikhar Ahmed S/0 Nazar Muhammad, M/S Barsa Cash & Carry Under Section 39 of Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against IESCO Regarding Detection Bill (Ac#24 14123 0983000, 24 14123 0983202 and 24 14123 0983206) Complaint # IESCO-27/2014

View

28-04-2014

Decision in the Matter of Complaint filed by Ms. Shagufta Nasreen under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against IESCO regarding Notice from IESCO for replacement of Metter and Change of Tariff. Complaint # IESCO-110/2013 View

07-03-2014

Decision int he Matter of Complaint filed by Mr. Sohail Nasim under section 39 of the Generation, Transmission and Distribution of Electric Power Act, 1997 against IESCO regarding dishonest abstraction or Consumption of Energy. Complaint # IESCO-107/2013 View

29-08-2013

Decision of Member (Consumer Affairs) in the matter of Complaint Filed by Mr. Asif Ali Raja, Director Al-Qadir Textile Mills Limited under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power At, 1997 against IESCO regarding Shifting of Meter from Premises to Grid Station. Complaint # IESCO-80/2012 View

13-04-2011

Complaint of Brig. Bashir-ud-Din (Retd.) under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against IESCO regarding Provision of Connection to the Inhabitants of the Judicial Town an Reinforcement of the System. 

Complaint # IESCO-138/2010

View

24-05-2010

Complaint of Mst. Hawas Noor Begum W/o Malik Sher Bahadur (Late) against IESCO regarding Non-Provision of Electricity Connection.

View

30-04-2010

Complaint of Power Consulting Engineers on Behalf of Metro Cash & Carry, Islamabad against IESCO regarding change of Billing from the Grid Station to Consumer Premises View

27-04-2010

Complaint of Qari Abdul Qadoos Abbasi against IESCO regarding Replacement of Damaged Transformer View

12-02-2010

Decision on Show Cause Notice to IESCO on the Complaint of Main Akram Farid, Managing Director, Pak Iron Factory against IESCO

View

23-10-2009

Complaint filed by Chief Engineer T.D.C.P against SDO IESCO Patriata sub division New Murree regarding unscheduled shut down and threats of Disconnection of Electricity Supply.

Complaint # IESCO-29/2009

View

01-01-2009

Review Petition filed by IESCO against the Decision of the Authority in the Matter of Major (R) Abdul Wahab Vs IESCO

View

17-06-2008

Complaint Filed by Maj. (R) Abdul Wahab (General Secretary) Citizen Community Board, Rawalpindi against IESCO regarding  extension of Electricity facility to the deprived residents of Pir Mehar Ali Shah Colony Rawalpindi.

View

03-06-2008

Complaint filed by Ch. Muhammad Arif Chairman District Public Safety and Police against IESCO regarding Installation of 100 KVA Transformer at Anara Kalli, Koh-e-Noor Hall Jhelum

View
K-Electric (Formerly KESCL)
23-12-2016 Order in the matter of complaint filed by Mr. Barkat Ali under section 39 of the Regulation Of Generation, Transmission And Distribution of Electric Power Act, 1997 against K-Electric Limited regarding arrears in the bill (Consumer # AL-382345) Complaint # KE-2119/2015 View
20-12-2016 Order in the matter of complaint filed by Mr. Rao Abdul Sami Khan under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric limited regarding detection bill (Consumer # AL-343088) Complaint # KE-616/2015 View

21-11-2016

Order in the Matter of Complaint filed by Elahi Electronics through Danish Elahi Chief Operating Officer  under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Charging of Sponsered Dedicated Distribution System (SDDS) Charges. Complaint # KE-320/2015 View

16-11-2016

Order in the Matter of Complaint filed by Mr. Abdi Hussain under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bill (CONSUMER # LB-233073) Complaint # KE-10/2016 View

16-11-2016

Order in the Matter of Complaint filed by Mrs. Hameeda Begum  under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Arrears in the Bill (CONSUMER # AL-171884) Complaint # KE-20/2016 View

16-11-2016

Order in the Matter of Complaint filed by Mr. Muhammad Hanif S/o Wali Muhammad  under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Arrears in the Bill (CONSUMER # AL-837680) Complaint # KE-2034/2016 View

16-11-2016

Order in the Matter of Complaint filed by Mr. Zahid Ramzan under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding KE Inspection Team Attitude and Wrong Billing (CONSUMER # LA-772496) Complaint # KE-96/2016 View

16-11-2016

Order in the Matter of Complaint filed by Mr. Muhammad Younis S/o Juma Bhai under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Assessed Billing & Detection Bill (CONSUMER # LA-932707) Complaint # KE-2104/2015 View

11-11-2016

Order in the matter of Complaint filed by Mr. Abdul Qayyum Under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bills. (CONSUMER # LA-014855) Complaint # KE-2006/2016

View

09-11-2016

Order in the matter of Complaint filed by Mr. Sarwar Zubari Under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bills (CONSUMER # LA-927731) - Complaint # KE-110/2016

View

09-11-2016

Order in the matter of Complaint filed by Mr. Gul Muhammad Ansari Under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bills (CONSUMER # LA-239195) Complaint # KE-2108-2015

View

26-10-2016

Order in the matter of Complaint filed by Mr. Saleem Ahmad Under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bills (AL-238511, AL-134517 & AL-434216) Complaint # KE-6.44 :2015

View

07-10-2016

Order in the matter of Complaint filed by Syed Sultan Shah Under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bills (Consumer # LA-583012) Complaint # KE-2009/2016

View

07-10-2016

Order in the matter of Complaint filed by Engr. Syed Muhammad Abid Under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bills (Consumer # LB-004257) Complaint KE-2091/2016

View

03-10-2016

Decision in the matter of complaint filed by Mr. Adam Masoori under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric limited regarding Arrears in the Bill (AL-908529) Complaint # KE-621/2015 View

03-10-2016

Decision in the matter of complaint filed by Mr. Rajab Ali under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric limited regarding Arrears in the Bill (AL-984788) Complaint # KE-02/2015 View

03-10-2016

Decision in the matter of complaint filed by Syed Hassan Ali Naqvi under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric limited regarding Arrears in the Bill (LA-490151) Complaint # KE-543/2015

View

03-10-2016

Decision in the matter of complaint filed by Mr. Naseem Rasool Hashmi under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric limited regarding Arrears in the Bill (AL-714081) Complaint # KE-2089/2015

View

31-08-2016

Decision in the matter of Complaint filed by Industrial Consumers of K-Electric under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding issuance of Notices on Account of Under-utilization of Sanctioned Load.

View

22-07-2016

Decision in the matter of Complaint filed by Muhammad Nadeem s/o Hanif Under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bill. Complaint # KE-2082/2015

View

22-07-2016

Decision in the matter of Complaint filed by Ahmed Chari s/o Khudad under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding arrears in bill. Complaint # KE-2038/2015

View

01-07-2016

Decision in the matter of Complaint filed by Mr. Sohail Ahmed Qureshi Under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bill. Complaint # KE-2062/2015

View

03-02-2016

Decision in the matter of Complaint filed by Mr. Haq Nawaz Shaikh Under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection Bill. Complaint # KE-286/2015

View

29-12-2015

Decision in the matter of Complaint filed by Mr. Muhammad Ilyas under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection bill. Complaint # KE-1117/2014

View

13-11-2015

Decision in the matter of Complaint filed by Ms. Jamal Rasheed, Chairman Public Sector Utilities, Power and Gas Sub-Committee - KCCI on Behalf of M/S Hamecare textile Under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Sponsored dedicated distribution system (SDDS) Charges.

Complaint # KE-178/2015

View

03-11-2015

Decision in the matter of Complaint filed by Mr. Khaliq Ur-Rehman under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection bill. Complaint # KE-1104/2014

View

28-10-2015

Decision in the matter of Complaint filed by Ms. Naseema Khatoon under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited regarding Detection bill. Complaint # KE--524/2014

View

27-10-2015

Decision of the authority in the matter of motion for Leave for review filed by K-Electric Limited against the Decision of NEPRA dated 13th march 2015 regarding bank Collection Charges of Rs. 8/- charged by K-Electric Limited. View

05-10-2015

Decision in the Matter of Complaint filed by Mr. Ali Raza s/o Habib Shah C/o Mr. Muhammad Ghayoor under section 39 of the regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Limited Regarding Detection Bill. Complaint # KE-2031/2015 View

18-09-2015

Decision in Pursuance to the Orders of Honorable High Court of Sindh at Karachi dated August 20, 2015 in C.P No. D-4710/2015: Seema Parveen Khan Vs NEPRA and others. Complaint # KE-77/2015 View

01-09-2015

Decision of the authority regarding motion for Leave for review filed by K-Electric Limited against NEPRA's decision dated 14th January 2015 in the matter of complaint filed by M/s Dreamworld Resort, Hotel & Golf Course. Complaint # KE-371/2014 View

06-07-2015

Decision of the Authority in the matter of Review Motion filed by K-Electric Limited against the Decision of NEPRA regarding complaint filed by Mr. Muhammad Qamar on behalf of Mr. Mazhar Hussain under section 39 of the regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-ELECTRIC Limited for arrears in the bill (consumer#AL203227) Complaint # KE-276/2014 View

09-06-2015

Decision in the matter of compliant filed by Ch. Mohammad Ashraf on behalf of S. M. Yousuf under section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric regarding detection bill (Consumer # AL-123206) — Complaint # KE-74/2014

View

01-06-2015

Decision In The Matter Of Compliant Filed By Sheikh Nisar Ahmed Parchamwala through Mr. Jameel Iqbal Syed, General Secretary, Anjuman-E-Mutassareen-E-K-Electric Karachi Division Under Section 39 Of The Regulation Of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric Regarding Arrears in The Bill - Complaint # KE-889/2014

View

01-06-2015

Decision in the matter of compliant filed by Mr. Abdul Waheed under Section 39 of the Regulation Of Generation, Transmission and Distribution of Electric Power ACT, 1997 against K-Electric regarding excessive billing / detection bill (Consumer # AL-467147 & LA-361824 - Complaint # KE-445/2014

View

07-05-2015

Decision of the authority regarding motion for leave for review filed by K-Electric Limited against the decision of NEPRA in the matter of complaint filed by S.M. Kaleem Makki, regarding detection bill

View

20-04-2015

Decision of the Authority in the matter of review motion filed by  K-Electric Limited under Rule 5 of NEPRA (FINES) Rules, 2002 against NEPRA Decision dated 22nd January 2015 in the matter of Show Cause notice under Rule 4(8) & (9) of NEPRA (Fines) Rules, 2002 regarding Charging of meter rent.

View

27-03-2015

Decision in the matter of Complaint filed by Mr. Muhammad Qamar on behalf of Mazhar Hussain under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 Against K-Electric Limited regarding arrears in the bill. Complaint # KE-276/2014 View

27-03-2015

Decision in the matter of Complaint filed by Mr. Muhammad Salman under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 Against K-Electric Limited regarding arrears in the bill. Complaint # KE-402/2014

View

13-03-2015

Decision of the Authority regarding Bank Collection Charges of Rs.8/- Charged by K-Electric Limited (formerly KESC). View

13-03-2015

Decision in the matter of Complaint filed by M/S Gulf Dying Mill's under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 Against K-Electric Limited regarding Withdrawal of Enhanced Load/ Issuance of Disconnection Notice and Demand of Rs. 1,493,208 on account of SDDs. Complaint # KE-66/2014

View

22-01-2015 Decision of the Authority in the matter of Show Cause Notice under Rule 4(8) and 4(9) of the NEPRA (Fines) Rules, 2002 regarding Charging of Meter Rent by K-Electric Limited (Formerly KESC)

View

16-01-2015 Decision in the Matter of Complaint Filed by Director, Dream World Resort, Hotel & Golf Course under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric  Limited regarding delay in Provision of Connection. Complaint # KE-371/2014 View
16-01-2015 Decision in the Matter of Complaint Filed by Mr. Muhammad Naseer Vohra under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric  Limited Change of Name/ Tariff and Excessive Billing. Complaint # KE-367/2013 View
09-12-2014 Decision in the Matter of Complaint Filed by Dr. Mushtaq Noorwala under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric Regarding Disconnection of Electricity Supply.Complaint # KE-188/2014 View
01-12-2014 Decision in the Matter of Complaint filed by Mr. S. M. Kaleem Makki under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric regarding Detection Bill. Complaint # KE-97/2014 View
18-09-2014 Decision in the Matter of Complaint Filed by Mrs. Asma Khalid under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric Regarding Tariff Dispute. Complaint # KE-235/2014 View
02-09-2014

Decision of the Authority Regarding Motion for Leave for Review filed by M/s Ali Brothers Against the Decision of NEPRA in the matter of complaint tiled by M/s Ali Brothers against K-Electric Limited for Detection Bill Complaint # KE-340/2013

View
29-08-2014

Decision in the Matter of Complaint Filed by Dr. Syed Raza Ali Gardezi under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric Limited Regarding Charging for Replacement of Burnt Meter (Consumer# AL032658)

Complaint # KE-379/2013

View

26-08-2014

Decision in the Matter of Complaint Filed by Mr. M. Ovais lqbal Baloch, Director VSH News under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric Limited Regarding Billing Dispute Complaint # KE-247/2014

View
08-08-2014

Decision in the Matter of Complaint Filed by Mr. Shahid Jamal, under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric Limited Regarding Detection Bill (Consumer # AL 672678) Complaint # KE-05/2014

View
08-08-2014

Decision in the Matter of Complaint Filed by Mr. Kamran Ahmed Siddiqui, under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against K-Electric Limited Regarding Arrears in the Electricity Bill (Consumer # AL 835247) Complaint # KE-515/2013

View
02-09-2014 Decision of the Authority Regarding Motion for Leave for Review filed by M/s Ali Brothers Against the Decision of NEPRA in the matter of complaint filed by M/s Ali Brothers against K-Electric Limited for Detection Bill. Complaint # KE-340/2013 View
23-04-2014 Decision in the matter of Complaint filed by Syed Ghulam Haider under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against K-Electric Regarding Detection Bill. Complaint # KESC-444/2013 View
17-04-2014

Decision in the Matter of Complaint Filed by Mr. Kamran Hussain Mughal, Director Coordination, M/s Popular Juice Ind. (Pvt.) Limited under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Feeding Provision.

Complaint # KESC-375/2013

View
16-04-2014 Decision of the Authority regarding Motion for Leave for Review filed by K-Electric (Formerly KESC) against the Decision of Member (Consumer Affairs) in the Matter of Complaint Filed by Mr. Ghulam Nabi  Detection Bill. Complaint # KESC-25/2013 View
14-04-2014 Decision of thr Authority Regarding Motion for Leave for Review filed by K-Electric (Formerly KESC) against Decision of Member (Consumer Affairs) in the Matter of Complaint Filed by Mr. Muhammad Arif Bilvani under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Average Billing. Complaint # KESC-232/2013 View
25-02-2014 Decision in the Matter of Complaint Filed by Syed Muhammad Hamid Raza under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Excessive Billing. Complaint # KESC-237/2013 View
25-02-2014 Decision in the Matter of Complaint Filed by M/s Ali Brothers under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bill. Complaint # KESC-340/2013 View
02-01-2014 Decision in the Matter of Complaint Filed by Mr. Ghulam Nabi under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bill. Complaint # KESC-25/2013 View
02-01-2014 Decision in the matter of Complaint Filed by Mr. Muhammad Arif Bilvani under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Average Billing. Complaint # KESC-232/2013 View

13-12-2013

Complaint Filed by Mr. Abdul Hameed Khan under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bill. Complaint # KESC-212/2013

View
30-05-2013 Decision in the matter of Complaint Filed by Mr. Hasan Farhan Syed under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bill. Complaint # KESC-453/2012 View
27-11-2013 Complaint Filed by Dr. Mohammad Tahir Soomro Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Excessive Billing. Complaint # KESC-365/2012 View
02-10-2013 Complaint filed by Mr. Khalil Ahmed Shaikh under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Excessive Billing and Arrears in the Bill. Complaint # KESC-23/2013 View
30-09-2013

Complaint filed by Mr. Nooruddin under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bill.

Complaint # KESC-177/2013

View
30-09-2013 Complaint filed by Mrs. Naheed Shaukat under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Arrears in the Bill. Complaint # KESC-156/2013 View
10-09-2013 Decision of Member (Consumer Affairs) in the Matter of Complaint Filed by Mr. Tajammul Hussain Chishti, Executive Director, Naurus Pvt. Ltd. under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bill. Complaint # KESC-154/2013 View
01-08-2013 Decision of the Authority on Motion for Leave for Review Filed by KESC against the Decision of Member (Consumer Affairs) in the Matter of Complaint of Mr. Uzair Ahmed Memon Regarding Arrears in the Bill. Complaint # KESC-214/2012 View
29-08-2013 Decision of Member (Consumer Affairs) in the Matter of Complaint Filed by Mr. Amir Ahmed Sethi under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bills. Complaint # KESC-423/2012 View
24-04-2013

Decision of the Authority on Motion for Leave for Review Filed by KESC in the Matter of Complaint Filed by Mr. Muhammad Ameen under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against KESC regarding Detection Bill.

Complaint # KESC-254/2012

View
24-04-2013 Decision of the Authority on the Motion for Leave for Review Filed by KESC in the Matter of Complaint Filed by M/s Qasim Textiles under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against KESC regarding Issuance of Notice for Un-Authorized Extension of Load. Complaint # KESC-85/2012 View

24-04-2013

Decision of the Authority on the Motion for Leave for Review Filed by KESC in the Matter of Complaint Filed by Mr. Abubakar Usman for M/s Greytex under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against KESC regarding Demand of Rs. 1,233,465. Complaint # KESC-158/2012

View
03-04-2013 Decision in the Matter of Complaint filed by Mr. Uzair Ahmed Memon under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against KESC regarding arrears in the Bill. Complaint # KESC-214/2012 View
11-02-2013 Decision in the Matter of Complaint filed by Mr. Khalid Mehmood under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against KESC regarding arrears in the Bill. Complaint # KESC-219/2012 View
21-01-2013 Decision in the matter of Complaint filed by Mrs. Saeeda Mazhar under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Arrears in the Bill. Complaint # KESC 335/2012 View
21-01-2013 Decision in the matter of Complaint filed by Mr. Sumair Mufti under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against KESC regarding Detection Bill. Complaint # KESC-146/2012 View
21-01-2013 Decision in the matter of Complaint filed by M/s Qasim Textiles  under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding issuance of Notice for unauthorized extension of Load. Complaint # KESC-85/2012 View
17-12-2012 Decision of Member (Consumer Affairs) in the Matter of Complaint Filed by Mr. Muhammad Iqbal under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against KESC regarding Excessive Billing. View

17-12-2012

Decision of Member (Consumer Affairs) in the matter of Complaint filed by Mr. Muhammad Ameen under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bill.

View
17-12-2012 Decision of Member (Consumer Affairs) in the Matter of Complaint Filed by Mr. Muhammad Fayyaz  under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against KESC regarding replacement of Electricity Meter & Detection Bill. View
27-11-2012 Decision of Member (Consumer Affairs) in the Matter of Complaint Filed by Mr. Abubakar Usman for M/s Greytex under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against KESC regarding Demand of Rs. 1,233,465 View

08-11-2012

Decision of the Authority in the matter of Review Motion filed by Mr. I.R. Sheikh against Order of the Member (Consumer Affairs) regarding Complaint filed by Mr. I.R. Sheikh under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC for Detection Bill. Complaint # KESC-22/2012

View
10-10-2012

Complaint filed by Mst. Shafqat Ara under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Excessive Billing.

Complaint # KESC-41/2012

View

09-10-2012

Complaint of Mr. Yawar Abbas under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Extra Amount in the Bill.

Complaint # KESC-11/2012

View
27-08-2012 Decision of the Authority Regarding Motion for Leave for Review filed by KESC against Decision of Member (Consumer Affairs) with respect to Complaint Filed by Mr. Muhammad Ayub Shaikh against KESC regarding Arrears in the Electricity Bill amounting to Rs. 113,835. View

17-08-2012

Order in the matter of Complaint filed by Mr. Muhammad Khalid under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bill.

View
16-08-2012 Order in the matter of Complaint filed by Mr. Sohail Anwar under Section 39 of the Regulations of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding View
08-08-2012 Decision of the Authority in the matter of Motion for Leave for Review filed by KESC against Decision passed by Member (Consumer Affairs) with respect to complaint filed by M/s Jalal Empire Welfare Association against KESC regarding Provision of Electric Connection to Jalal Empire D-32, Al-Hilal Co-operative Housing Society Karachi. Complaint # KESC-32/2011 View
02-07-2013 Decision of Member (Consumer Affairs) in the Matter of Complaint Filed by Mr. Zulfiqar Ali  under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Excessive Billing. Complaint # KESC-440/2012 View
28-06-2012

Complaint filed by Mr. I.R. Sheikh under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Detection Bill.

Complaint # KESC-22/2012

View
15-05-2012 Order in the Matter of Complaint Filed by Mr. Mohammad Ayub Shaikh under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC regarding Arrears in the Electricity Bill amounting to Rs. 113,835. Complaint # KESC-20/2012 View
16-04-2012 Order in the Matter of Complaint Filed by Mr. Muhammad Riaz under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against KESC . View
Faisalabad Electric Supply Company (FESCO)

11-11-2016

Order in the Matter of Complaint filed by Mr. Zafar Iqbal  under Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against FESCO regarding Detection Bill (A/C NO. 06 13466 0387400 R) FESCO-66/2016

View

24-06-2016

Decision of the Authority Regarding Appeal Filed by Gravity Mills Limited under Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against the Order of the Appellate Board dated June 12, 2015 in the Matter of FESCO Vs Gravity Mills Limited.

View

07-02-2014

Complaint filed by Mr. Amal Badshah under Section 39 of the regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against FESCO regarding Detection Bill and Restoration of Electricity Supply.  Complaint # FESCO-33/2013

View

19-12-2013

Decision in the Matter of Complaint filed by Mr. Allah Dad S/o Muhammad Khan under Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against FESCO regarding Detection Bill. Complaint # FESCO-24/2013

View

21-05-2013

Decision in the Matter of Complaint filed By Mr. Muhammad Bilal Khan S/o Sher Bahadur Khan under Section 39 of THe Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against FESCO regarding Non-Provision of New Connection and Additional Demand Notice.

Complaint # FESCO-82/2012

View

20-12-2012

Complaint filed by Mr. Shahid Rahim, representative all shop owners & tenants, Kohinoor one Plaza, Jaranwala road, Faisalabad under section 39 of the regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 regarding over-charging of Electricity Bills and Disconnection of Electricity Supply of Shop No. 87. Complaint # FESCO-38/2012

View

02-07-2012

Review Petition filed by FESCO against against the Decision of the Authority in the matter of Complaint of Mr. Nasrullah Khan S/o Ahmad Khan regarding Detection Bill View

08-03-2012

Complaint of Mr. Nasarullah Khan S/o Ahmad Khan Forwarded by Sheikh Waqqas Akram Minister of State under Section 39 of the regulation of Generation, Transmission, Transmission and Distribution of Electric Power Act, 1997, against FESCO regarding Detection Bill. Complaint # FESCO-70/2011

View

05-07-2011

Decision in the matter of Complaint filed by Ms. Tayyab Textile Mills (Pvt.) Limited under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against FESCO regarding Extension of Load. Complaint # FESCO-04/2011 View

15-03-2011

Complaint of Mr. Zafar Jalil Khan under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against FESCO regarding Non- Provision of Electricity Connection. View

22-06-2010

Complaint of Mr. Haq Nawaz Khan S/o Barkat Ali Khan against FESCO regarding Non-Provision of Electricity Connection. View
Gujranwala Electric Power Company (GEPCO)

28-07-2015

Decision in the Matter of Complaint filed by Rana Mahmood Iqbal s/o Abdul Sattar Rana under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against GEPCO regarding Detection bill and Removal of Electricity Meter. Complaint GEPCO-2/2016 View

31-07-2015

Decision in pursuance to the Directions of the Honorable Lahore High Court Lahore in writ petition / Criminal original no. 1595-w/2015 in the matter of Sajjad Sarwar and Muhammad Bashir vs NEPRA, WAPDA Employees Co-operative Housing Society Gujranwala (WECHS) and GEPCO

View

31-07-2015

Motion for Leave for Review filed by Secretary WAPDA Employees Co-operative Housing Society Gujranwala (WECHS) against the decision of NEPRA in pursuance to the Directions of the Honorable Lahore High Court in writ petitions No. 22622/2013 and No. 29982/2013 in the Matter of WECHS vs GEPCO. Complaint GEPCO-26/2012 View

05-03-2015

Decision in pursuance to the directions of Honorable Lahore High Court in writ petitions no. 22622/2013 and no 29982/2013 in the matter of WAPDA employees Co-operative Housing Society, Gujranwala vs GEPCO. Complaint GEPCO-26/2012

View

18-12-2012

Decision of the Authority in the Matter of Motion for Leave for Review filed by GEPCO against the Decision Passed by Member (Consumer Affairs) with respect to Complaint filed by District Officer Building Division Hafizabad under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against GEPCO regarding delay in provision of Electricity Connection.

View

16-08-2012

Order in the Matter of Complaint filed by District Officer, Buildings Division, Hafizabad under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against GEPCO regarding Installation of Energy Meter at Govt. Rural Dispensary Kharak Bhattian, District Hafizabad. View

16-08-2011

Complaint filed by Mr. Abdul Basit Butt s/o Haji Karamat ullah Butt under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against GEPCO regarding Supplementary/ Additional Demand of Capital Cost Rs. 23,380. Complaint GEPCO-34/2-2011

View

15-03-2011

Complaint of Mr. Tariq Mahmood s/o Bashir Ahmad under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against GEPCO regarding issuance of Additional Demand Notice. Complaint GEPCO-71/2010

View

02-06-2010

Review Petition filed by Mr. Ghazanfar Iqbal against the Decision of Member (Consumer Affairs) regarding charging of Grid sharing cost and acquiring land by GEPCO. View

19-08-2009

Complaint filed by Mr. Ghazanfar Iqbal Aujla against GEPCO regarding charging of Grid Sharing Cost. View
Multan Electric Power Company (MEPCO)

28-07-2016

Decision in the Matter of Complaint filed by Imran Oil Mills through Sheikh Muhammad Imran s/o Sheikh Abdul Majeed under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against MEPCO regarding Detection  Bill View  

14-01-2016

Decision in the Matter of M/s SINCO Steel Re-Rolling Mills Private Ltd. under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997  against MEPCO Regarding Tariff Rationalization Surcharge and Financing Cost Surcharge

View  

07-12-2015

Decision in the matter of Complaint filed by M/s National Flour Mills (NFM) through Tasleem Akhtar, Managing Partner, NFM under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against MEPCO regarding Excessive Billing View  

03-11-2015

Decision in pursuance to the Orders of Honorable Lahore High Court, Bahawalpur Branch September 08, 2015 in Writ Petition No. 6776-2015/BWP: Mian Ehsan VS NEPRA etc

View  

29-09-2015

Decision of the Authority regarding Motion for Leave for Review filed by JDW Sugar Mills (JDWSML) against NEPRA's Decision dated 23rd December 2014 in the matter of complaint filed by M/s JDWSML against MEPCO regarding Renewal of Power Purchase Agreement (PPA) and Determination of Tariff Between MEPCO and JDWSML View  

13-02-2015

Decision in the Authority in the matter of Complaint filed by M/s JDW Sugar Mills Limited under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against MEPCO regarding Renewal of Power Purchase Agreement and Determination of Tariff View

25-02-2014

Decision in the Matter of Complaint Filed by Shahnaz Javed Rafi, Rafi Gardens Housing Society, Shaiwal under Section 39 of The Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against MEPCO regarding External Electrification of Rafi Gardens Housing Society. View

19-12-2013

Decision in the Matter of Complaint Filed by Mr. Muammad Hanif s/o Allah Diwaya under Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against MEPCO regarding Wrong Billing. View

10-07-2012

Decision of the Authority in the Matter of Motion for Leave for Review filed by MEPCO against the Decision Passed by Member (Consumer Affairs) upon a Complaint filed under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 by M/s. Azam Associates on behalf of Makkah Cotton Industries, Multan View

10-07-2012

Decision of the Authority in the Matter of Motion for Leave for Review filed by MEPCO against the Decision Passed by Member (Consumer Affairs) upon a Complaint filed under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 by M/s. Azam Associates on behalf of Rehman Cotton Industries, Multan View

10-07-2012

Decision of the Authority in the Matter of Motion for Leave for Review filed by MEPCO against the Decision Passed by Member (Consumer Affairs) upon a Complaint filed under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 by M/s. Azam Associates on behalf of Subhan Cotton Industries, Multan View

10-07-2012

Decision of the Authority in the Matter of Motion for Leave for Review filed by MEPCO against the Decision Passed by Member (Consumer Affairs) upon a Complaint filed under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 by M/s. Azam Associates on behalf of Rashid Furqan Cotton Factory, Multan View

15-03-2012

Complaints of M/s Azam Associates Regarding Change of Tariff and Wrong Demand in Case of M/s Makkah Cotton Industries View

15-03-2012

Complaints of M/s Azam Associates Regarding Change of Tariff and Wrong Demand in Case of M/s Rehman Cotton Industries View

15-03-2012

Complaints of M/s Azam Associates Regarding Change of Tariff and Wrong Demand in Case of M/s Subhan Cotton Industries View

15-03-2012

Complaints of M/s Azam Associates Regarding Change of Tariff and Wrong Demand in Case of M/s Rashid Furqan Cotton Factory. View
Lahore Electric Supply Company (LESCO)

19-11-2016

Decision of the Authority regarding Motion for Leave for Review filed by Lahore Supply Company Limited (LESCO) against the Decision of Member (Consumer Affairs) in the Matter of Complaint of Umer Spinning Mills (Pvt.) Limited Vs LESCO for Non-Refund/ Adjustment of Cash Security Deposit against Submission of  Bank Guarantee Complaint # LESCO-142/2015 View

19-10-2016

Order in the matter of Complaint filed on behalf of Mrs. Fazeelat Begum Under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Correction of Bill/Re-Installation of Connection (A/C # 19 11233 1578700 U) Complaint # LESCO-123/2015 View

19-10-2016

Order in the matter of Complaint filed by Qazi Masood Ur Rehman Under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Arrears in the Rill (A/C # 13 11545 1193403 11) - Complaint // LI .:SCO-106/2015 View

16-08-2016

Decision in the matter of Complaint filed by Nishat Mills Limited (NML) under section 39 of the Regulation of Generation Transmission and Distribution of Electric Power Act, 1997 against LESCO

View

14-06-2016

Decision in the Matter of Complaint filed by Umar Spinning Mills (Pvt.) Limited (Ac # 24 11223 9007002) under section 39 of the Regulation of Generation Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Non-Refund/ Adjustment of Cash Security Deposit Against Submission of Bank Guarantee

View

01-01-2016

Decision in the Matter of Complaint filed by Mrs. Rukhsana Aijaz s/o Aijaz Ahmed under section 39 of the Regulation of Generation Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Replacement of Defective Meter and Wrong Billing

View

22-10-2015

Decision in pursuance to the orders of Honorable Lahore High Court, Lahore dated September 08, 2015 in Writ Petition no. 26321/2015: Muhammad Shahzad etc vs NEPRA, LESCO

View

16-09-2015

Decision in the matter of complaint filed by Mr.Akhtar Ali Chaudhry, Executive Director, M/s Siara Textile Mills (Pvt) Limited under section 39 of the Regulation of Generation Transmission and Distribution of Electric Power Act, 1997 against LESCO Regarding extension of load and dedicated Feeder (AC # 27-11613-2604200R) Complaint # LESCO-103/2014

View

08-05-2015

Decision in pursuance to the directions of Honorable Lahore High Court in writ petition No.5327/2015: Rana Muhammad Ali vs Chief Engineer/Customer Services etc complaint #  LESCO-10/2015 View

24-02-2015

Decision of the Authority in the Matter of Review Motion filed by Siddique Trade Centre Lahore Against the Decision of NEPRA regarding Complain filed by M/s Goodi & Joyous and Mr. Axhar Abbas Shah & Others under Section 39 of Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against LESCO & Siddique Trade Centre for Charging of Higher Tariff View

12-02-2015

Decision in Pursuance to Orders of the Honourable Lahore High Court dated January 15, 2015 in the matter of Complaint filed by Mr. Muhammad Safdar s/o Muhammad Ashraf under Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Excessive Billing. View

13-01-2015

Decision in the Matter of complaint filed by Mr. Shahid Rasool s/o Ghulam Rasool under Section 39 of Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against LESCO Regarding Detection Bill View

28-10-2014

Decision in the Matter of complaint filed by Mr. Amjad Ali, Consultant, Zong, CMPak Ltd., under Section 39 of Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against LESCO Regarding Average Billing View

27-10-2014

Decision in the Matter of complaint filed by Mr. Muhammad Younis Sheikh under Section 39 of Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against LESCO Regarding Withdrawal of Excessively Charged Bills. Complaint # LESCO-70/2014 View

12-08-2014

Decision of the Authority in the Matter of Review Motion filed by LESCO Against the Decision of NEPRA in the matter of complaint filed by M/s Faster Consultant on behalf of Mian Zahid Rasool/Sheikh Mansoor Zafar under Section 39 of Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 Against LESCO Regarding Detection Bill. Complaint#LESCO-93/2013 View

25-04-2014

Decision in the Matter of Complaint Filed by Major General (R) Javed Iqbal, Chief Executive Officer, Punjab Industrial Estate Development & Management Company (PIEDMC), Lahore under Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Extension of Load. Complaint # LESCO-64/2013 View

11-04-2014

Complaint filed by Engr. Shahid A Bhatty (Chief Executive Orion Consultants) on behalf of Sui Northern Officers Cooperative Housing Society (SNOCHS) Lahore under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Extension of Load. Complaint # LESCO-135/2011 View

21-01-2014

Decision in the matter of Complaint filed by M/s Faster Consultants on behalf of Mian Zahid Rasool/ Sheikh Mansoor Zafar under Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Detection Bill. AC # 240135590010006.

Complaint # LESCO-93/2013

View

03-09-2012

Decision in the matter of Complaint filed by Rana Muhammad Ali under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Detection Bill. View

15-03-2011

Complaint of Mr. Abdul Haq s/o Wali Muhammad under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Non-Provision of Electricity Connection. Complaint # LESCO-141/2010 View

20-06-2012

Complaint filed by Lt. Col. Rizwan Akram against LESCO under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 regarding over Billing.

 Complaint # LESCO-175/2011

View

15-03-2011

Complaint of Mr. Abdul Haq s/o Wali Muhammad under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Non-Provision of Electricity Connection. Complaint # LESCO-141/2010 View

11-02-2011

Complaint of Mr. Usama Tariq Khan (President) Tariq Gardens Housing Scheme Lahore against LESCO regarding Removal of Old Poles of HT Lines. View

11-02-2011

Complaint of Mian Muhammad Iqbal s/o Mian Fazal Muhammad under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against LESCO regarding Issuance of Additional Demand Notice. Complaint # LESCO-01/2010 View

22-06-2010

Complaint of Syed Ashiq Hussain Naqvi against LESCO: Issuance of Excessive Demand Notice View

24-05-2010

Complaint filed by Engineer S.T. Hussain (Chief Executive) M/s Consumer Awareness and Welfare Association against LESCO regarding Notice for Disconnection of Electricity Supply View

24-05-2010

Complaint of Mirza Aurangzeb Babar s/o Mirza Aslam Baig against LESCO regarding Non-Issuance of Demand Notice for Provision of Tube well Connection

View

Quetta Electric Supply Company (QESCO)
 

02-12-2013

Dectsion in the Matter of Complaint filed by Mr. Faraz Hassan, M/S Gul Marble Factory under Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against QESCO Regarding Detection Bill. Complaint # QESCO-16/2012 View

20-11-2013

Complaint filed by Mr. Fakhrul Hasan, M/s New Gul Tiles Factory, Double Road, Quetta under Regulation of Generation, Transmission and Distribution of Electric Power Act 1997 against QESCO regarding Detection Bills . Complaint # QESCO-15/2013

View

Hyderabad Electric Supply Company (HESCO)

21-10-2016

Decision in the matter of Appeal filed by Zorlu Enerji Pakistan Limited (ZEPL) against Decision of the NEPRA Tribunal in the matter of Contractual Dispute between Hyderabad Electric Supply Company Limited and ZEPL. View

21-01-2016

Decision in the Matter of Complaint Filed by M/s Khas Textile Mills (Pvt.) Limited under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against HESCO regarding Fixed Charges/Cross Subsidy and Refund of Security Deposit.

Complaint # HESCO-153/2013

View

02-04-2013

Complaint Filed by Maj (R) Amir Ashraf Khan, Manager (Administration), M/s Island Textile Mills Limited - Hyderabad (ITML) under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against HESCO regarding Non provision of New Connection and Demand for payment of Fixed Charges (Amounting to Rs. 17360676). Complaint # HESCO-67/2012 View

27-08-2012

Complaint filed by M/s Popular Spinning Mills (Pvt.) Ltd. Jamshoro under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against HESCO regarding Refund of Fixed Charges/Cross Subsidy and Security Deposit.

View

27-08-2012

Complaint filed by M/s Popular Fiber Mills (Pvt.) Ltd under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against HESCO regarding Illegal Demand of Cross Subsidy/ Fixed Charges and Security Deposit. View

22-02-2011

Complaint of Major  (R) M. Saeed (Manager Admin) M/s Quetta Textile Mills Ltd. under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 against HESCO regarding Non-provision of New Connection and Demand for Payment of Fixed Charges. Complaint # QESCO-342/2010

View
Sukkur Electric Supply Company (SEPCO)
 
   No Complaints  
Peshawar  Electric Supply Company (PESCO)
 

24-08-2016

Decision in the Matter of Complaint filed by Bestway Cement Limited under section 39 of the Regulations of Generation, Transmission and Distribution of Electric Power Act, 1997 against PESCO Complaint PESCO- 106/2014

View
13-11-2015 Decision in the Matter of Complaint filed by General Manager & Project Director, Tarbela Dam under section 39 of the Regulations of Generation, Transmission and Distribution of Electric Power Act, 1997 against PESCO regarding Provision of Supply at One-Point. Complaint # PESCO-31/2015 View

16-09-2015

Decision in pursuance to the order of the Honorable Peshawar High Court Dated 25th March 2015 in writ Petition No. 2958-P of 2013: Mian Muhammad Ayaz and Others against Peshawar Electric Supply Company (PESCO) and others Complaint # PESCO-32/2015

View
03-10-2012 Complaint of Mr. Allah Wasaya s/o Muhammad Nawaz under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997, against PESCO regarding Illegal Billing. Complaint # PESCO-186/2011 View
29-05-2012 Decision of the Authority in the Matter of a Review Petition filed by PESCO against the Decision of Consumer Affairs Division regarding Complaint filed by Mr. Azizullah. Complaint # PESCO-91/2011 View
26-09-2011 Complaint of Mr. Azizullah under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997, against PESCO regarding Unjustified Electricity Bill. View
11-02-2011 Complaint of Dr. Akhtar Abbas s/o Niaz Hussain under Section 39 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997, against PESCO regarding shifting of HT Line Laying over the Roof of the Complainant. View
Tribal Area Electric Supply Company (TESCO)
 