28-10-2022 | Notification S.R.O. 738(I)/2022 -NEPRA hereby notifies the Decision of the Authority in the matter of Motion for Leave for Review filed by National Transmission & Despatch Company (Pvt.) Ltd. (NTDC) against the Determination of the Authority dated November 4, 2021 | |
16-09-2022 | Decision of the Authority in the matter of Motion for Leave for Review filed by National Transmission & Despatch Company (Pvt.) Ltd. (NTDC) against the Determination of the Authority dated November 4, 2021 | |
27-05-2022 | Notification S.R.O. 738(I)/2022 -NEPRA hereby notifies the Determination of the Authority in the matter of Petition tiled by National Transmission & Despatch Company Ltd. (NTDC) for Determination of Use of System Charge (UOSC) for the FY 2019-20, FY 2020-21 and FY 2021-2022 |
04-11-2021 | Determination of the Authority in the matter of Petition filed by National Transmission & Despatch Company Ltd. (NTDC) for Determination of Use of System Charge (UOSC) for the FY 2019-20, FY 2020-21 and FY 2021-2022 |
31-03-2020 |
Decision of the authority in the matter of motion for leave for review filed by National Transmission and Dispatch Company Limited with respect to the determination of the Authority dated July 31, 2019 |
31-07-2019 | Determination of the Authority in the matter of Petition filed by National Transmission & Despatch Company Ltd. (NTDC) for Determination of Transfer/Wheeling Charges for the FY 2017-18 and FY 2018-19 | View |
04-05-2018 | Decision of the Authority in the matter of Reconsideration Request filed by Ministry of Energy (Power Division) against Decision dated September 25, 2017 with respect to Transfer/Wheeling Charges | View |
25-09-2017 | Decision of the Authority in the matter of Motion for Leave for Review filed by National Transmission & Despatch Company Ltd. (NTDC) against Decision Dated April 11, 2017 with respect to Transfer/Wheeling Charges | |
03-08-2017 | Decision of the Authority in the matter of Induction of Security Cost for the CPEC Projects in the Power Tariff to Ensure Security Sustainability | |
11-04-2017 | Determination of the Authority in the matter of Petition filed by National Transmission & Despatch Company Ltd. (NTDC) for Determination of Transfer/Wheeling Charges for the FY 2015-16 and FY 2016-17 |
21-06-2016 | Decision of the Authority in the matter of Power Acquisition Contract filed by National Transmission & Despatch Company Ltd. for CASA-1000 Transmission Project under NEPRA Interim Power Procurement (Procedure & Standards) Regulations, 2005 | View |
12-02-2016 | Approval of Extension of Tariff effective from 1st January 2015 to 31st December 2015 in Contract dated 6th November 2002 between NTDC and TAVANIR, Iran for Supply of 74 MW | View |
22-01-2016 | Decision of the Authority with respect to Request for Re-calculation of Inadvertent Error in Calculation filed by National Transmission & Despatch Company Ltd. (NTDC) under Section 16(5) of NERPA (Tariff Standards and Procedure) Rules, 1998 (Tariff Rules) contained in the Reviewed Determination of the Authority dated 20th October, 2015 | View |
20-10-2015 | Decision of the Authority in the matter of Motion for Leave for Review filed by National Transmission & Despatch Company Ltd. (NTDC) against the Authority's Determination dated 23rd April 2015 | View |
03-08-2015 | Decision of the Authority in the matter of request for approval of Power Purchase Agreement containing tariff and terms and conditions for power procurement from 102-MW Gulpur Hydropower Project | View |
29-05-2015 | Approval of Power Acquisition Request filed by National Transmission and Despatch Company Ltd. (NTDC) for Import of Power 1000 MW from TAVANIR, Iran under the NEPRA Interim Power Procurement (Procedures and Standards) Regulations, 2005 | View |
23-04-2015 | Determination of the Authority in the matter of Petition filed by National Transmission & Despatch Company Ltd. (NTDC) for Determination of Its Transfer/Wheeling Charges for the FY 2014-15 | View |
09-04-2015 | Decision of the Authority in the matter of Request filed by National Transmission and Despatch Company Ltd. (NTDC) for approval of Power Procurement and Negotiated Advance Tariff at Feasibility Stage for 1100 MW Kohala Hydropower Project. | View |
10-11-2014 | Approval of Extension of Tariff effective from 1st January 2014 to 31st December 2014 in Contract dated 6th November 2002 between NTDC and TAVANIR, Iran for Supply of 74 MW | View |
16-10-2014 | Decision of the Authority in the matter of Motion for Leave for Review filed by NTDC against Decision of the Authority regarding Procurement of Power from 640 MW Azad Pattan Hydropower Project located in the State of Azad Jammu & Kashmir | View |
16-10-2014 | Decision of the Authority in the matter of Motion for Leave for Review filed by NTDC against Decision of the Authority in the matter of Procurement of Power from 500 MW Chakothi Hattian Hydropower Project | View |
30-01-2014 | Decision of the Authority in the matter of Power Acquisition Request filed by National Transmission and Despatch Company (NTDC) under the NEPRA Interim Power Procurement (Procedures and Standards) Regulations, 2005 for Permission to Negotiate Power Acquisition Contract in respect of 640 MW Azad Pattan Hydropower Project | View |
30-01-2014 | Decision of the Authority in the matter of Power Acquisition Request filed by National Transmission and Despatch Company (NTDC) under the NEPRA Interim Power Procurement (Procedures and Standards) Regulations, 2005 for Permission to Negotiate Power Acquisition Contract in respect of 500 MW Chakothi Hattian Hydropower Project | View |
19-07-2013 | Determination of the Authority in the matter of Petition filed by National Transmission & Despatch Company Ltd. (NTDC) for Determination of Its Transfer/Wheeling Charges for the FY 2012-13 | View |
18-07-2011 | Decision of the Authority with respect to Motion for Leave for Review filed under Rule 3(2) of the NEPRA (Review Procedure) Regulations, 2009 by National Transmission and Despatch Company Ltd. (NTDC) against the Authority's Determination dated 9th May 2011 | View |
09-05-2011 | Determination of the Authority in the matter of Transfer/Wheeling Charges under NEPRA (Tariff Standards and Procedures) Rules, 1998 for National Transmission and Despatch Company Ltd. | View |
06-01-2006 | Determination of Tariff in respect of M/s National Transmission and Despatch Company Ltd. intimation of determination of Tariff to Section 31(4) of the Regulation of Generation, Transmission and Distribution of Electric Power Act (XL of 1997) | View |
15-02-2005 | Decision of the Authority Regulatory Meeting RM 05-013 in respect of Power Purchase Agreement (PPA) between Iqbal Power Ltd (Rajdhani Hydropower) and National Transmission and Despatch Company Ltd. (NTDC) | View |
14-04-2004 | Determination of Tariff in respect of M/s National Transmission and Despatch Company Ltd. intimation of determination of Tariff to Section 31(4) of the Regulation of Generation, Transmission and Distribution of Electric Power Act (XL of 1997) | View |
13-04-2004 | Decision of the Authority regarding Extension of one month in the period for Determination of Tariff Petition filed by National Transmission and Despatch Company (NTDC) | View |